Feasibility study
Preliminary design
Detailed design
Structural calculations
Execution drawings
External development / landscaping
Tender documentation
Authorization and approval applications
Site meetings and handover of works
Safety coordination
Quantity survey control
Final design and project dossier
Contact
Construction of a data center meeting security requirements according to Tier IV criteria.
Contracting authority Post Luxembourg
Etude 2009-2018
Construction 2010-2018
Key features
Structural stability and building engineering studies
Earthworks: 120,000 m³
External development / landscaping
Eco-friendly parking areas
Asphalt-paved traffic lanes
IT area: 5,000 m²
Environmental risk analysis
Innovative energy concept
Facilitation of safety meetings
Verification of compliance with occupational health and safety standards
Preparation and monitoring of safety plans
Intervention during redevelopment works