• Installation of photovoltaic panels of 469.5 kWp
• Work in proximity to high-voltage overhead lines
Contact
Installation of carports with photovoltaic panels in the employee parking lot at Creos’ main site in Roost. We carried out the safety coordination mission on-site in accordance with the Grand-Ducal regulation of 27 June 2008.
Contracting authority Enovos Luxembourg S.A.
Etude 2023
Construction 2023
• Participation in design meetings and site meetings
• Preparation and updating of the General Safety and Health Plan (PGSS)
• Preparation and adaptation of the preliminary notice
• Coordination meetings
• Verification of the Particular Safety and Health Plans (PPSS)
• Regular site visits with visit reports
• Preparation of the dossier adapted to the characteristics of the structure (DAO)