Installed capacity of 392.70 kWp
Installation on a flat roof with a risk of working at height
Low-voltage connection (400 V)
Construction site adjacent to the parking facility currently under completion
Contact
Safety and health coordination mission on site, in accordance with the Grand-Ducal regulation of June 27, 2008.
Construction of a rooftop photovoltaic installation on the “LoopPark” open-air parking, with a capacity of 392.70 kWp.
Contracting authority Enovos Luxembourg
Etude 2023-2024
Construction 2024
Key features
Our missions
Participation in project design meetings
Preparation and updating of the preliminary notice
Preparation and updating of the General Safety and Health Plan (GSHP)
Review of Specific Safety and Health Plans (SSHPs)
Regular site visits based on critical phases and risk analysis
Preparation of the file adapted to the characteristics of the structure (DAO)