Dust Extraction System

After dismantling the dust extraction system from its former plant in Florange (France) piece by piece, ArcelorMittal will reassemble it at the ArcelorMittal Long Products Luxembourg site in Differdange.
Connected to industrial extraction hoods positioned as close as possible to the most emission-intensive processes, the system will capture the maximum amount of dust at the source. It will be capable of extracting 1,200,000 m³ of air per hour and is expected to reduce diffuse dust emissions by up to 80%.

This unusual relocation required the execution of structural and civil engineering works to accommodate the installation at the Differdange site.

  • Contracting authority ArcelorMittal Belval & Differdange SA

  • Etude 2022-2023

  • Construction 2023-2025

Key features

  • Chimney with 5.50 m diameter at the base, 36 m height

  • 600 m of bored piles

  • 100 t of reinforcement (piles + structures)

  • 800 m³ of earthworks

  • 1,500 m² of external development in an industrial site

Our missions

  • Execution of structural and civil engineering studies for the new facility

  • Coordination meetings

  • Study of the existing environment

  • Structural design (piles, pile caps, grade beams, pile-supported slabs, chimney base)

  • Calculations and execution drawings (formwork and reinforcement)

  • Quantity schedule / bill of quantities

  • Studies and rerouting of existing utility networks